Billed as the tallest building in the world, the task of providing services to the Burj Dubai was always going to be a challenge. The world records made by the project stretch to the services themselves, with the longest lift run in the world being among them, despite this, the aim of providing constant services is involving the use of proven technologies and close logistics.
MEP senior manager of Samsung-Besix-Arabtec joint venture, Rachid Ghamraoui explains: “One thing that is very important in this project is that we are using proven design enhanced to suit the project needs from the height and configuration of the building.” This decision to opt for up-to-date technology comes from the need to ensure constant operation of services in all foreseeable eventualities.
“All [MEP] equipment has been checked and calculations made for anti-seismic, anti-vibration and to take into account the deflection and the movement of the building,” explains Ghamraoui.
Due for completion in December 2008, the Burj Tower is already one of the tallest in the Middle East, currently standing at over 100 storeys. The final structure will be over 160 storeys tall, with a floor area of 465,000m
2
and will include an Armani-designed hotel, residential apartments, boutique offices and commercial spaces.
Its shape is based on an indigenous desert flower, with three distinct wings protruding from a central core that stretches the full height of the building, the wings gradually decreasing with height creating a spiral effect.
Chigaco-based architect SOM designed the building for client Emaar, with Turner Construction acting as project manager. The main contractor’s role on the project is being undertaken by an integrated joint venture between Besix, Samsung and Arabtec.
The major MEP works for the permanent installation is being carried out by ETA, Voltas and Hitachi under a joint venture contract, with several client-nominated subcontactors carrying out other packages, such as the extra low voltage system by Johnson Controls.
The scale of build and three-day per floor speed of construction has meant that the close co-ordination between contractors plays a major role in the project and all have been site-based from the start of construction. “The logistics will be a very, very important issue here,” stresses Ghamraoui. In addition to ensuring materials and labour can reach the correct height when needed, the tight space around the tower must also be considered.
“Very soon the external works comprising of irrigation, landscaping and special water features will commence, which will further limit the available space,” explains Ghamraoui. “We have to organise ourselves in order to store the material at site in a proper way or to get it stored outside and move it to the building at the right time to get it directly to the right locations,” he adds.
The heart of the building from the mechanical services viewpoint is at level B2, which feeds a main riser in the central core, and in turn, sub-risers in the building’s wings. Chilled water is supplied to the building from a district cooling plant that also serves the adjacent Dubai Mall and Lake Tower Hotel.
The supply of chilled water to the tower is carried out by a forced pump system. The primary chilled water is received from the EMAAR district cooling plant at 3.3°C at level B2. It is then passed through a series of heat exchangers before being pumped to a plantroom at level 17, and thereafter to further plantrooms at levels 40, 73, 109 and 139. “The water is then distributed from the respective plantrooms to air handling units and fan coil units located in apartments and guestrooms” explains Ghamraoui.
The domestic water supply and fire sprinkler system work under the principle of gravity, with water being pumped to the water tanks in the upper level mechanical rooms for further distribution.
“This whole concept is almost like an umbrella – you provide at one location and then distribute downwards. This is a unique concept and is achievable merely due to the available gravity from the very high height of the building,” Ghamraoui adds.
“One thing that was very important [to the MEP distribution] was the structure of the building,” stresses Ghamraoui. “With the huge thickness of walls, from a builders’ work point of view, we had a challenge not to miss any of the holes or openings.” This meant the early involvement of the MEP contractors was vital, as was their co-ordination with the civils contractors.
The length of pipe runs through the main riser also meant that the system design had to consider the movement of the building as well as natural expansion and contraction of both the pipes and building structure. A specialist subcontractor was appointed under the MEP scope of works to study the pipe movements and advise on the positioning of expansion joints and guides. “For every single pipe we made a calculation for the vertical part, every angle and deviation,” stresses Ghamraoui.
Rather than a conventional gravity support system, pipe guides and ball joints are installed at various storeys, thus enabling free movement of the pipework within the building taking into account seismic, building deflection, vibrations and acoustic requirements. This design means that a single stanchion at the base of the system supports the weight of the water and pipework. With a load of 140 tonnes at this point, careful design was needed. “The elbow [at the base] is a very special piece…the thickness is much higher than any elbow normally used and it is of a higher grade of steel,” explains Ghamraoui.
With an 84MVA total capacity to meet, supplying electrical power to the Burj has meant an unusual system being applied. Rather than step-down transformers reducing the power voltage at the hv incoming supply, here an 11kV power supply is distributed throughout the building via the main riser. This is reduced to a 400V supply at substations located throughout the building, then distributed by busbar via sub-mains distribution boards, which finally feed local distribution boards via corridor routes. A four-core, 180mm
2
diameter cable was chosen for the hv distribution as the flexibility of tap-off points given by busbar was not required.
To ensure total security of supply there are two main electrical risers located in the building core – one for standard and the other for emergency power – that operate in parallel. Five 2200kVA generators provide further back-up to the life safety systems in the event of a total power failure.
Not surprisingly with the tower design of the building, vertical transportation is a major factor in the MEP services. A total of 54 elevators and eight escalators are being installed under a subcontract package awarded to manufacturer Otis.
Included within this design is the longest lift tunnel in the world, which will see a double-deck lift run from the ground to a visitor’s area at levels 122 and 123 that will house restaurants, bars and an observatory deck. This is also one of the fastest double-deck lifts in design and will operate at a speed of 10m/s. “This was specially developed in order to cope with the amount of people that are likely to want to visit this iconic building,” explains Ghamraoui. “In a double-deck you can put more people in a limited space.”
Fire lifts with speeds of 9m/s will serve all floors of the building. Access to higher floors via the general elevators, as is standard for towers, requires users to transfer between two or more lifts to reach their destination; speeds for these lifts range from 1.75-7m/s.
The positioning of major MEP plant at height required careful planning due to the construction methods being used and the future replacement of plant. “The construction of the tower is something special from the civils point of view,” states Ghamraoui, “The whole building is under jump form, there is shuttering everywhere, so if we want to introduce equipment we cannot do it from the top.
“Some of the equipment weighs over 10-15 tonnes, therefore loading platforms capable of receiving this weight will be installed at various plantroom levels projected outside of the building,” he adds.
To enable the speed of structural construction to continue unhindered, the MEP contractor has opted to crane in large-scale pipes from the top of the building directly into the central core.
“We are installing chilled water pipe that is 600mm diameter and 12m in length, the weight is around 3500kg in one piece,” explains Ghamraoui, “We found a way to make an opening within the jumping form in order to introduce those huge pipes and minimise the welding joint numbers on site; it’s a very special method using intermediate hoists inside the tower.”
Removal of the plant at the end of its lifespan has also been considered. Plantrooms are located adjacent to the service lifts, with the elevators sized to cater for the largest sized section of plant that must be removed – the transformers. “It has also been looked at from a layout point of view: the routing from the plantroom to the elevator is free of any equipment, so we don’t have to stop operating any installation, you just dismantle the plant and get it replaced,” stresses Ghamraoui.
To get the quantities of materials supplied for the project was a task in it itself, with over 4,000 fan coil units alone (see box ‘Burj Dubai: the figures’). “That was one of our achievements – we can say today for this project that almost 95% of the materials are already approved and orders are in place,” says Ghamraoui.
“One thing that is very important in such a huge project is the team spirit. If everyone does not look to the same targets in a positive spirit we cannot achieve this project. But I can say with certainty this spirit is there,” he concludes.
•
121,000
light fittings;
•
170
pumps;
•
34km
chilled water pipework;
•
4000
fan coil units;
•
140
air handling units;
•
3600
fans;
•
52
heat exchangers;
•
225,000
chilled water pipe fittings;
•
33,000
chilled water valves;
•
86MVA
electrical load;
•
1.8 million metres
of conduit;
•
55km
cable tray;
•
1.5 km
of busbar;
•
250km
lv cables;
•
20km
of mv cables;
•
71
transformers;
•
5000
façade lights;
•
375km
fire alarm cabling;
•
10,000TR
cooling load.
The final MEP installation in the Burj Tower is only half of the services storey. With over 2,500 people employed on site and 24/7 construction operations, services had to be installed from the start of the project to ensure that construction programmes and safety standards could be met.
“Power, firefighting services and water supply should be operational 24 hours [during construction] and it’s very important to have something safe and reliable,” stresses Ghamraoui. “It must also be flexible because the building is moving, so you have to keep the power supply at the higher level even if it is under construction,” he adds.
A third demand on the temporary systems was ease of operation. “We are completing one floor every three days, so the power supply, firefighting and water supply should follow the same speed as the construction.
“We started the temporary MEP works well in advance of the permanent ones,” explains Ghamraoui. These are being designed and installed by an entirely separate team of operatives that are employed directly by the Samsung-Besix-Arabtec joint venture rather than under the MEP contractors’ package. This is done in order to cope with the flexibility of construction.
The size of temporary works involved here dwarf final installations on many projects. Pumps of up to 32 bar are being used for water supplies, with five 600kW and three 110kW generators plus three 1,000kVA substations dedicated to the electrical supplies.
To get materials and labour to the areas needed, 18 of the final lifts are being used. In addition, eight external lifts of 1.6m/s and three internal ‘jumping’ lifts are being used, the latter being moved up the building with the structural formwork. The building shape and jumping form construction method mean that other than the lifts, the only access point for materials is through the roof and for heavy equipment projected loading platforms are installed at different plantroom levels.
“One of the challenges is to have a proper logistics plan in order to get the people and the materials to the right location at the right time. We have to make it to save time for the workers and get the job done…the higher [the building] becomes the more time it will take to take people and material to their location,” Ghamraoui explains.
The temporary wet-water systems installed mirror that of the final installation, with operation by gravity feed. For the firefighting systems, water is pumped from ground level to two high-level 24m
3
water tanks and at every floor a fire hose reel and a landing valve are installed. “The difficulty here is that we must also provide firefighting on all of the wooden platform jumping formwork,” stresses Ghamraoui. “It is very important for us to protect this jumping form because it is the most important equipment in the civil works process,” he adds.
The domestic water supply follows this system also, using the same tanks to supply toilets and kitchens by gravity feed. “At every floor we have urinals, washbasins and toilets. Also, in order to avoid people having to go down to ground level, the canteen areas will be located at the intermediate floors in the building [during construction] and for that we are providing water,” states Ghamraoui.
These temporary tanks will be dismantled and removed following completion of the permanent systems. It was not possible to use the final tanks during this stage as the products were not available, but more importantly, the area in which they will be positioned is yet to be built.
Client
: Emaar Properties PJSC
Project manager/management contractor
: Turner Construction International
Main contractor
: Samsung-Besix-Arabtec JV
Architect and designer
: Skidmore, Owings and Merrill
Supervision consultant
: Hyder Consulting Middle East
MEP contractor
: ETA- Voltas-Hitachi Plant JV
Lighting designer
: FMS
Lift contractor
: Otis
ELV contractor
: Johnson Controls
Contract Details
Completion date
: December 2008
Suppliers
AHUs: Klimak
BMS
: Honeywell
Boilers
: Hurst
Cable
: Ducab, Riyadh Cable
Cable management
: Barton, KSC
Chillers
: Lennox
Controls
: Honeywell
Control valves
: Honeywell
Drainage
: National Plastics, Spears
Ductwork
: Emirates Ducts, Weathermaker
Electrical accessories
: Crabtree
Electrical distribution
: ABB
Emergency luminaries
: CEAG
Extract fans
: Penn
Fan coil units
: Carrier
Fire alarm/detection
: Honeywell
Floor grilles
: Trox
Flues
: Midtherm
Heat exchangers
: Alfa Laval
HV switchgear
: ABB
Insulation
: Cape East, Kimmco
Lighting controls
: i-Light or Dynalite (TBA)
LV switchgear
: ABB
Power busbar
: Cutler Hammer, Eaton
Pumps
: Grundfos, KSB
Pressurisation
: Armstrong
Sound attenuation
: Prime Tech
Sprinklers
: NAFFCO
Standby generation
: Caterpillar
VAV boxes
: Solid Air
Water heaters
: AO Smith