The Sharjah Electricity, Water, and Gas Authority (SEWA) announced the commencement of operations at the 33/11 KV Kalba Commercial Power Transmission Station.
This will enhance power transmission and distribution networks across all areas, providing the best services to the residents of Sharjah.
The operations at the Kalba station commenced following the successful completion of all testing and commissioning processes.
Youssef Mohammed Al Hammadi, Director of Kalba Department at SEWA, said the authority executed the project to the highest standards and within a specified timeline.
“The new 33/11 kV commercial substation in Kalba is the main source of electrical supply for the region and neighbouring areas, including the commercial and industrial zones, Al Qurm, Kalba Mall waterfront, Victoria School, and the Khatm Al Melahia border point,” he said.
Al Hammadi said the station is equipped with advanced systems to ensure quality and efficiency, and has a capacity of 60 MVA.
The station features a BMS (Building Management System) that includes access control, surveillance cameras, air conditioning systems, room temperature monitoring, and fire suppression systems.